Q2 Strategic Risk Report

Meeting: 26/11/2020 - Governance and Audit Committee (Item 20)

20 Q2 Strategic Risk Report pdf icon PDF 155 KB

To provide an update to the Committee on the progress of the Council’s identified strategic risks (report of the Executive Manager Growth)

Additional documents:

Minutes:

Consideration was given to the report of the Executive Director Strategy and Governance, which provided an update to the Committee on the progress of the Council’s identified strategic risks.

 

The report aimed to present an overview of the strategic risks identified by the Council, approach to mitigations and risk scores associated with the risks. The report included, at Appendix 1, a more detailed Strategic Risk Register document This was the first risk report presented to the Committee since the Coronavirus pandemic, and was a significantly changed document from previous versions.  It covered a new set of areas that had arisen as a result of the pandemic including the risks of dealing with more than one specific event at the same time in addition to the challenges around the Covid pandemic, the potential impact on the economy, the ability to conclude Council business, decision making in a virtual way, and business continuity in key areas such as waste collection. 

 

Officers pointed out that the report stated that there were 27 strategic risks with 12 at a medium score. However the number of risks with a low score was stated as 18 however this should have been 15.     

 

As this was the first iteration of the document in the current Covid situation, comments from the Committee were welcomed.

 

Members considered the report, and the following issues were raised:

 

·         The report was useful however there was a great amount of detail within it which was not easily read on an electronic device. 

  • Officers stated that they would work to produce the information in a more user-friendly format.

·         Members responded that the Strategic Risk Register itself had much detail on it and needed to be produced in an A3 paper format for consideration at future meetings.

  • Officers replied that this could be done.

 

·         There did not appear to be a definition of what constituted red, amber or green risks.

  • Officers advised that this information was detailed within a grid at the end of the spreadsheets within Appendix A

 

·         Technology and infrastructure failure – in view of the fact that recently, email had not been available for a number of days, should the impact of this risk be changed?

  • Officers advised that due to the sensitive nature of this item, the risk owner would provide all members with details outside of the meeting, of the issues around this particular incident.

 

·         The Authority was offering financial support to the leisure provider, Parkwood, until the end of December – this date was approaching quickly.  Was this mitigation changing?

  • The current negotiating position with the contractor ran until the end of December. The Authority was working with the contractor to obtain a model for the impact on the business to the end of quarter 4 and this was also being updated to reflect the impact of the announcement today regarding the introduction of tier 3 restrictions.  The Authority was awaiting the opportunity to bid into some funding from the Department of Culture, Media and Sport.  Members would  ...  view the full minutes text for item 20