2021/22 Financial Report Quarter 3

Meeting: 26/04/2022 - Cabinet (Item 52)

52 2021/22 Financial Report Quarter 3 pdf icon PDF 129 KB

To provide information on the Quarter 3 (to 31 December 2021) financial position of the Council (report of the Portfolio Holder for Finance, Commercialisation and Partnerships and the Deputy Chief Executive (Corporate Development) and S151 Officer enclosed).

Additional documents:

Minutes:

Consideration was given to the report of the Portfolio Holder for Finance, Commercialisation and Partnerships and the Deputy Chief Executive (Corporate Development) (S151 Officer), which provided information on the Quarter 3 (to 31 December 2021) financial position of the Council.

 

The Portfolio Holder for Finance, Commercialisation and Partnerships provided the following summary:

 

·         The Q3 Forecast Outturn 2021/22 presented the forecast outturn position as at 31stDecember 2021 for this financial year and was based on the information known at the time.

·       General Fund - The full year forecast outturn based on current projections and assumptions was an overspend of £191,000 in the General Fund, which included the balances of unachieved efficiency savings of £397,000.  The forecast outturn position by Directorate was detailed at Appendix A – Table 1, together with an analysis of service variations.  The 2021/22 budget included an efficiency savings target of £1.676 million, savings achieved so far were £1.279 million. Details of these savings were listed in Appendix A table 2a.

·         Reserves (GF and HRA) - General Fund Specific Reserves were forecasting a decrease of £0.311 million from £13.493 million to £13.182 million - further details were set out in Appendix A - Table 3.  In addition, the General Fund Reserve Balance remained at £2.078 million.  The HRA General Reserve balance was forecasting an overall increase of £0.846 million from £27.384 million to £28.230 million. More details were provided at Appendix A – Table 3.

·         HRA - The HRA was forecasting a surplus of £1.663 million, and further detail was provided at Appendix A - Table 4.

·         Capital

o   General Fund - Revisions totalling £0.922 million were recommended for approval, as detailed in Appendix A Table 5, giving a revised 2021/22 programme of £8.390 million.  The total budget carry forward due to slippage on the General Fund Capital Programme of £3.747 million was detailed on Appendix A – Table 8was recommended for approval.

o   HRA - The total revised HRA Capital Programme for 2021/22 was £14.984 million as detailed in Appendix A Table 10.  The total budget carry forward due to slippage on the HRA Capital Programme of £9.281 million as detailed on Appendix A – Table 12was recommended for approval.

·         Treasury Management - Appendix A - Section 2.5 provided details of the Council Treasury Investments. As at 31 December 2021, a total of £48.376 million investments were held by the Council. Appendix A Table 13 provided more information on the investments.  The forecast income from investment interest had been calculated at £194,000, as per budget.

·         Debt Collection - Section 2.6 showed the analysis of sundry debts the Council held as at 31st December 2021.

·         Council Tax & Business Rates - Section 2.7 

o   Council Tax - Collectable debit for 2021/22 was £54.4 million.  As at December 2021, collection rate was 83.55% (83.80% at 31 December 2020)

o   Business Rates - Collectable debit for 2021/22 was £24.1million.  As at December 2021, collection rate was 81.59% (77.99% as at 31 December 2020)

 

It was noted  ...  view the full minutes text for item 52