Consideration was given to the report of the
Assistant Director for Finance and Deputy S151 Officer, and the
Interim Assistant Director for Governance and Monitoring Officer,
to introduce a new updated version of the Contract Procedure Rules
and an amendment to the Financial Procedure Rules.
The Head of Procurement and Contracts
introduced the report by referring to the amendments which applied
to South Holland District Council, and outlined in Appendix 1A as
follows:
- the single change to the exemption
clauses were outlined at point 3.3.9 of the report. The proposed
change allowed for a reasonable exemption to assist with the
development of housing, where this was considered appropriate;
and
- revised thresholds were outlined at
point 9 of the report.
The Head of Procurement and Contracts
presented the following case study which demonstrated how the
exemption stated at point 3.3.9 of Appendix 1A could be
utilised:
“The Council
could pursue the purchase of housing through a ‘package
deal’ which would incorporate planning consent, land purchase
and build. Initially, a third party obtained the planning consent,
secured the legal interest in the land, and secured a work
contractor to build for a fixed price. On the date that planning
consent was granted, the Council would enter into a simultaneous
agreement to purchase the land and enter into a Joint Contracts
Tribunal (JCT) contract with the works contractor at an agreed
price. Should a package deal be pursued, the benefits to the
Council included:
- engagement in the project from an
early stage; and
- the undertaking of a quality and
value-for-money assessment prior to involvement.
The inclusion of
the exemption clause enabled different housing delivery routes to
be pursued/explored by the Council. If the authority were to pursue
a package deal, formal approval for each specific scheme would
always be required from either the Executive or the
Council”.
Members considered the report and made the
following comments:
- Members asked how Cabinet members
obtained specialist knowledge when making such decisions.
- The Assistant Director –
Finance stated that the exemption resulted from legal advice which
had been sought for a new type of housing delivery
option. External advisers provided
technical advice where this was not available within the skillset
of officers.
- Members queried the process that
would be followed for the purchasing of properties should the
proposed exemption not have been brought forward as an amendment.
- The Head of Procurement and
Contracts stated that the purchase of a housing package would not
be possible, and the Council would need to source land in the
traditional way, or procure completed properties direct from
developers. The exemption enabled Council involvement from
commencement of a scheme and therefore control over the quality of
the build.
- The Assistant Director –
Finance stated that whereas previously a builder may have
approached the council directly, the exemption enabled a builder to
work with a partner, such as a Housing Association, to put forward
a package deal to the Council.
- Members asked whether the Council
had considered utilising framework agreements, such as those
provided by SCAPE.
- The Head of Procurement and
Contracts confirmed that the options to use frameworks had not
changed and would be utilised where this was the best option.
.
- Members welcomed the changes which
offered new delivery opportunities. Nonetheless, it was requested
that external advice be taken with projects to mitigate against
issues that national companies had faced.
- Members asked for clarification of
point 4.2.2 of the report regarding the disposal of land - did this
apply solely to land, or to both land and property?
- The Head of Procurement and
Contracts confirmed this applied to both land and property
- Members referred to point 5.2 which
listed records to be kept for tendered contracts of between
£40,0000 and £85,000 in value and asked why records
were not kept for all values. Additionally, point 5.3 stated that
records kept for contracts up to £40,000 ‘should be
proportionate to the value of the contract’ however it was
not clear how proportionality was assessed, and the approach was
subjective.
- The Head of Procurement and
Contracts stated that the vagueness relating to point 5.3 would be
removed.
- Members asked who would approve, and
therefore be accountable for, a Capital Programme spend of
£209,000.00
- The Assistant Director –
Finance responded:
- that approval would depend on the
nature of the programme. Spend that related to several projects
over various schemes of work, would be approved on a case-by-case
basis;
- a decision could be made by a
Portfolio Holder or an officer with delegated powers;
- any ‘Key Decision’ spend
would be subject to the governance process; and
- whilst the Procurement and Contracts
team assisted with the procurement process, the responsibility of
the design and project management of the scheme would remain with
the client officer.
- The Head of Procurement and
Contracts stated that spend on a single project would involve an
assessment of the case with the client officer which included:
- whether the use of a framework was
applicable;
- which local contractors could
potentially be utilised; and
- whether a tender process was
necessary.
.
- Members referred to the
£40,001 to £85,000 threshold stated at point 9 of the
report and requested the addition that at least three quotations be
received.
- The Assistant Director –
Finance stated that:
- a minimum requirement had not been
stipulated since a failure to achieve a stated number of quotations
would delay progression of the project;
- the Procurement Team applied an
extra layer of scrutiny to ensure that appropriate quotations were
received; and
- the value-for-money assessment was
wider than cost alone and also considered: quality; employment
opportunities such as apprentices; and social values.
- Members considered the response but
were not comfortable with the absence of a minimum quotation
requirement and requested that at least two quotations be required.
An exception could be considered where a single/limited supplier(s)
existed, in which case the exemption process could be followed.
- The Assistant Director - Finance and
Head of Procurement and Contracts would consider the practicalities
and feasibilities of the request. The request would also be raised
when the item was scrutinised by Governance and Audit committees
across the partnership.
- Members referred to the e-Tendering
process as noted at point 5.2, and asked, for the benefit of all,
whether responses to individual queries were circulated to all
interested parties.
- The Head of Procurement and
Contracts confirmed that this was the case and full transparency
was applied.
- Members asked whether the tender
form included a declaration of a close relationship with a
Councillor/officer.
- The Head of Procurement and
Contracts would ensure that this was included for
transparency.
- Members asked whether the policy
change needed to be scrutinised by the Policy Development Panel?
- The Assistant Director –
Finance responded that Contract Procedure Rules were part of the
constitution and therefore the report process of Governance and
Audit, Cabinet and Council had been followed. This process would be
checked with the Monitoring Officer.
- Members queried whether the
exemption stated at point 3.3.3 could lead to unscrutinised
extension of contracts/a monopoly situation.
- The Head of Procurement and
Contracts stated that various levels of scrutiny were employed to
ensure that this would not occur.
- Members referred to Appendix 2 which
outlined the proposed amended delegations to officers in relation
to contracts, and asked for clarification of the changes.
- The Head of Procurement and
Contracts responded that the sole change for South Holland District
Council related to the inclusion of split limits for the signing of
contracts under seal. This was already stated in the Constitution
and had been included in the procedure rules for transparency.
- Members thanked officers for the
report and pre-briefing presentation which had facilitated their
understanding of the proposed changes. It was requested that future
proposed changes to existing procedures be highlighted within any
report coming forward to committees for consideration.
AGREED:
a)
That following consideration of the draft revised Contract
Procedure Rules at Appendix 1 to the report, the draft proposals be
noted;
b)
That the suggestion that the Monitoring Officer be authorised to
make the necessary changes to update the Council’s
Constitution, accordingly, including delegation to amend where
inconsistencies arise, noting that the CPR will take primacy, be
noted by the Governance and Audit Committee;
c)
That the recommendation for Council to approve the revised
financial procedure rule for Banking arrangement and cheques as
detailed in Paragraph 1.12 of the report be noted by the Governance
and Audit Committee; and
d)
That the comments of the Governance and Audit Committee which
related to points 5.3 and 9 of Appendix 1A, be noted.