Consideration was
given to the report of the Director – Economic Development
which asked the Panel to provide feedback on the progress of the
public consultation.
The Heritage Manager
and the Director – Economic Development attended for this
item.
The Heritage Manager
presented the report and provided the Panel with a detailed update
on the progress of the public consultation relating to a suite of
heritage documents as set out in the report including:
- Spalding
Conservation Area Appraisal and Management Plan (including the
Spalding Shopfront Design Guide)
- Spalding
Heritage Strategy
- Holbeach
Conservation Area Appraisal and Management Plan
- S&ELCP
Traditional Building Design Guide
It was noted
that:
The documents sat
across two portfolio areas — Heritage & Conservation and
Planning.
- The
consultation had commenced in November 2025 and had included social
media campaigns, press and site notices, letters to properties
proposed for inclusion or removal, and public events held in both
Spalding and Holbeach. Hard copies had been made available on
request, which included Members and the Civic Society. Documents
were also accessible on the Council’s consultation webpage
and via the planning portal:
- Although
the formal six?week consultation period had elapsed, the documents
remained online to allow further comment. The Heritage Manager
noted a lack of responses from Spalding town centre businesses,
prompting further engagement coordinated with the Spalding BID.
Additional engagement was planned with the Spalding Town Board on 9
February 2026. All comments were requested by 13 February 2026 to
allow a consolidated submission to consultants; and
- The
Heritage Strategy and the Traditional Building Design Guide served
as guidance only documents and had no formal adoption.
Members considered
the report and made the following comments:
·
Members
queried the lack of responses from Spalding town centre businesses
during the consultation.
o
The
Heritage Manager explained that while initial engagement was low,
an additional event had been held with Spalding BID and further
outreach undertaken. It was suggested that businesses may have felt
unaffected due to no proposed changes to conservation area
boundaries, or because many were not owner?occupiers. The consultation remained
open until 13 February 2026 and further responses might still be
received.
- Members
asked had the follow?up engagement yielded improved responses from
businesses, and what proportion as a percentage had responded
overall.
- The
Heritage Manager reported that a handful of attendees had attended
the BID event along with two email comments, but the total number
of businesses as a percentage figure was not available to report at
the meeting.
- Members
commended the clarity of the documents and asked about formal
sign?off.
- The
Heritage Manager confirmed the documents were in a draft format and
that formal sign?off arrangements would be addressed once
amendments had been made to where possible incorporate consultation
responses at the final stage.
·
Members referred to
the Spalding Conservation Area Appraisal and noted that public
comments suggested that resources should focus on improvements to
the existing conservation area rather than an extension of it.
Could specific detail of the feedback be provided.
o
The Heritage Manager
reported that residents commonly raised issues related to the
condition of windows, doors and materials on residential properties
and explained that such matters currently fell under permitted
development rights, limiting the Council’s control, but that
the management plan identified possible mechanisms for increasing
restrictions. Feedback had included the use of residential Grant
Schemes to assist with costs.
·
Members asked how
licensing regulations relating to visibility into shopfronts might
interact with planning control in conservation areas.
o
The Heritage Manager
confirmed that licensing and planning were separate legal regimes
and that licensing considerations had not been assessed as part of
the appraisal.
·
Members raised
concerns about the map quality within the Spalding and Holbeach
appraisals and asked whether higher?resolution mapping could be provided.
o
The Heritage Manager
acknowledged the comment and confirmed that
higher?definition mapping would be explored for future versions to
aid readability.
- Members
asked how many conservation area appraisals were being consulted
across the partnership, and what were the cost implications of
completing the remainder.
- The
Heritage Manager stated that seven appraisals were out to
consultation across the S&ELCP. They were exploring ways to
deliver the remaining appraisals, which typically cost
£5,000–£15,000 each, depending on size of the
area.
- Members
referred to the Holbeach Conservation Area Appraisal and queried
whether residents affected by the proposed extensions been
contacted directly, and if so were response levels known.
- The
Heritage Manager confirmed that direct letter?drops to properties
within the proposed additions/removals area had been delivered
along with multiple site notices. Around five responses had been
received for Holbeach, which was broadly consistent with response
levels seen in other areas.
Relating to the
Spalding Shopfront Design Guide, members raised the following
questions;
- Members
queried whether the Spalding Shopfront Design Guide be
district?wide rather than Spalding?specific.
- The
Director – Economic Development, advised that the Spalding
Shopfront Design Guide had been funded via the Spalding Town Board
and appended to the Spalding appraisal, hence its limited
geographic scope. A partnership?wide treatment was being progressed
in the separate S&ELCP Traditional Building Design Guide, which
provided generic guidance across the area.
- Members
asked whether feedback from businesses included both independents
and multinationals traders and what input was received.
- The
Director – Economic Development, explained that the Business
Improvement District covered all businesses in scope, with several
local businesses engaging at the provided sessions. Feedback
focused less on specific design points and more on historic
enforcement concerns and wider management issues.
- Members
referred to the Shopfront Guide and queried whether its application
as ‘material consideration’ would deter multinationals
or disadvantage local independents if their corporate branding
conflicted with the guide.
- The
Director – Economic Development and the Heritage Manager
explained that economic development and planning colleagues had
typically worked with corporate applicants and design teams to
secure acceptable, brand?compliant solutions. In conservation
areas, proposals must preserve or enhance; the guide would provide
solutions rather than impose a blanket prohibition. Proposals that
preserved character should be supported; enhancements were sought
where preservation was not achieved. Decisions would be made on
planning merits rather than business type.
- Members
asked what resources and capacity would be available to enforce the
Spalding Shopfront Design Guide.
- The
Director – Economic Development responded that the document
was a guide and not enforceable.
o
The Heritage Manager noted a step?change
in conservation staffing since March: a full?time Principal
Conservation Officer now worked wholly on conservation (previously
split role), and a second full?time Conservation Officer post had
been shared across the partnership, along with the appointment of
an Assistant Conservation Officer. It was noted that while formal
planning enforcement sat with the Enforcement Team, the
Conservation Team could now draft robust conservation responses to
support notices and would look to handle simpler cases more
proactively as capacity allowed.
- Members
asked if officers were actively striving for enhancement rather
than mere preservation in day?to?day casework.
- The
Heritage Manager confirmed that, for every application within a
conservation area, they would assess whether proposals preserved or
enhanced. Where applications did not preserve in the first instance
then officers would seek enhancements. For sites not currently
proposing works, it was recognised that there was a need for
proactive engagement (including potential grants and proactive
enforcement) to encourage improvement.
- Members
asked whether officers could pursue the enhancement of prominent
buildings such as the former Johnson Hospital.
- The
Heritage Manager confirmed that the aspiration to improve key sites
was reflected in the Heritage Strategy and wider regeneration
plans, and proactive measures would be explored.
- Members
referred to the placeholder images in the S&ELCP design guide
and asked if these could be replaced with local photographs.
- The
Heritage Manager advised that the placeholders would be replaced
with local photographs to illustrate examples from within the
partnership area.
AGREED:
a)
That the comments of the Panel be noted;
and
b)
That the proposed course of actioned,
which involved further consultation, subsequent amendments to the
documents and placing before Cabinet for approval, be
supported.