The Regional Engagement Manager and
Pre-Development Planning Manager from Anglian Water provided a
comprehensive presentation as attached at Appendix A to these
minutes.
Members considered the presentation and made
the following comments:
- As Anglian Water was obliged to
create a connection, how could they object to an application that
would likely be approved or introduce a condition that prevents
occupation of a property until a connection is agreed to.
- The Pre-Development Planning Manager
responded that pre-occupation conditions, called a Grampian
condition, had been tested in the courts and should be a
consideration in the planning process. Local Plan policies did
include infrastructure capability as a consideration when
determining applications.
- It was appreciated that Anglian
Water were one of many consultees (non-statutory) and they
didn’t want to prevent growth but needed to be sure that the
environment was not negatively affected by this growth.
- There was a danger that the local
authority would not be able to deliver the housing targets set by
the government.
- Where water recycling centres (WRC)
were labelled ‘at capacity’, did this refer to normal
flow or excess rainfall?
- The Pre-Development Planning Manager
confirmed that this was determined on average flow put back into
the environment which changed year on year. Conversations were
ongoing with the regulators and government on how to move forwards
with this.
- Did the objections made by Anglian
Water only to major applications?
- The Pre-Application Development
Manager confirmed this applied to both major and minor
applications.
- The Regional Engagement Manager
added that once a permit had been exceeded, no further connections
could be made. Funds were not available to deliver infrastructure
improvements at the rate required due to the regulator capping
customer bills and increased housing numbers since Anglian
Water’s current five year business plan (2025-2030).
- Significant investment had been made
into the infrastructure in Sutton Bridge, what stage was this at?
- The Pre-Development Planning Manager
confirmed that this WRC was green and therefore had capacity to
accept new connections and the WRC was compliant with the dry
weather flow element of the permit.
- What was the effect on isostatic
discharge and to what extent would pumps be installed to assist
with the tides, given rising sea levels?
- The Pre-Development Planning Manager
agreed to take the question regarding isostatic discharge
away.
- The Regional Engagement Manager
responded that long term adaptations and delivery strategies were
in place looking 25 years ahead. Resilience was built into the
asset delivery programme and Anglian Water had the most highly
monitored network.
- Risks were always a factor, and
reservoirs were being built above sea level to try and combat these
effects.
- Did Anglian Water reclaim minerals
and drugs out of the water?
- The Regional Engagement Manager
responded that everything that went into the WRC’s was
recyclable, but that they did not reclaim minerals and drugs from
waste water. All waters and solids were recycled, and gas was
extracted from this process generating energy to help power the
operational site.
- Science was developing to remove
things such as microplastics and forever chemicals – PFAS
from water but currently Anglian Water were working to the permits
provided by the government.
- Was there a historical lack of
investment in water infrastructure in South Holland?
- The Regional Engagement Manager
commented that water was a privatised industry where customer bills
had been managed by Ofwat determinations of water company
investment plans so private investment had been sought. Since
Covid, expectations had changed, particularly with regard to the
environment, that Anglian Water were now trying to keep up
with.
- Previously, more money had been
invested in water resilience to keep clean water and avoid hosepipe
bans but this had now shifted to a focus on environmental
improvements based on customer feedback and tightening
environmental regulations.
- How many times had a planning
application been refused due to an objection by Anglian Water?
- The Pre-Development Planning Manager
responded that the pre-application condition had only been in place
for a year so was relatively new. Anglian Water were now using
planning legislation to try and prevent new connections rather than
the Water Industry Act.
- The Regional Engagement Manager
added that Anglian Water were engaging with more planning case
officers and offering to speak to both them and planning
committees.
- What were the timescales for any
investment intentions in WRC’s currently labelled as amber.
- The Pre-Development Planning Manager
indicated that the ambers asked for a planning condition which was
connected to the Anglian Water business plan and growth schemes
outlined within it. Schemes within this plan would be delivered by
2030 but no timeframes were available for each individual
investment.
- Were the indicated improvements
works minor or major?
- The Pre-Development Planning Manager
confirmed that these were all major works costing millions of
pounds each. It was a complex process involving design,
pre-application with the Environment Agency and permit
regimes.
- It was noted that development would
naturally go to any areas that were labelled as amber or green.
- The Pre-Development Planning Manager
acknowledged that these would be more attractive areas for
developers.
- Should investments have been planned
for areas currently labelled as red, given that the local plan had
only been adopted recently?
- The Pre-Development Planning Manager
responded that a growth scheme would only have been asked for in
those that are amber. No condition would be requested for reds as
it would not be dischargeable.
- Would any refusal based on an
Anglian Water objection hold up on appeal?
- The Pre-Development Planning Manager
responded that Anglian Water were prepared to attend any appeal to
provide expert witness testimony.
- Legal opinion also supported this,
and it had already been established that this was a material
planning consideration.
- The KC opinion regarding a
pre-occupation condition could be provided to members as some
authorities were already applying this.
- How much capacity did the
WRC’s listed as green actually have?
- The Pre-Development Planning Manager
agreed to provide this information to Members.
- It was noted that development type
was looked at when considering any objections to applications in
these areas so capacity could differ based on this factor.
- It appeared a holding situation was
in place until 2030 when upgrades to infrastructure had occurred in
amber areas as there were no other areas to place new development.
- The Pre-Development Planning Manager
responded that Anglian Water were currently lobbying government to
use local plan information to inform growth schemes.
- They were currently asking for local
authority planning officers to sit on a working group considering
long term growth as part of the Drainage and Wastewater Management
Plan to influence this.
- Some residents in areas that were
labelled red would be happy that no there was no further capacity
but this would not assist the local authority in achieving its
house building targets.
- What would happen if the local
planning authority refused to put the pre-occupation condition on
the application?
- The Pre-Development Planning Manager
confirmed that this risk would need to be managed, and engagement
would be required with the Environment Agency about pollution.
- The Regional Engagement Manager
added that the Environment Agency could prosecute Anglian Water for
pollution.
- What if developers were to install
their own package treatment plant on site?
- The Pre-Development Planning Manager
confirmed that this was an option where descriptive works were
allowed but approval of the Environment Agency was required..
- It was noted that the Environment
Agency policy was to approve in rural areas but unlikely to do so
in urban areas.
- Pleased that this was Anglian
Water’s position as infrastructure needed to be in place to
build new houses and it was a shame that other bodies didn’t
do the same.
- Concern was raised as to the
consequences on the authority should housing delivery targets not
be met.
- The Regional Engagement Manager
commented that a balance needed to be struck between development
certainty and improving infrastructure.
- The Pre-Development Planning Manager
added that Anglian Water were constrained by the regulators cap on
customer bills as these funded WRC investment growth schemes.
- Was there a connection charge for
developers?
- The Pre-Development Planning Manager
responded that a connection charge was in place to physically make
the connection and also an infrastructure charge purely for foul
networks across the whole region, not for the WRC’s.
- Did Anglian Water bill payers pay
the fines for WRC’s being over capacity?
- The Regional Engagement Manager
confirmed that shareholders paid the fines, but they would be less
likely to invest if Anglian Water was regularly being fined.
- What was the possibility of Anglian
Water adopting a private sewerage treatment works?
- The Pre-Development Planning Manager
agreed that a conversation could be undertaken outside of the
meeting.
- It was important that the
information provided by Anglian Water be circulated to MPs.
- The Regional Engagement Manager
responded that a blueprint for growth would be published in January
to set out challenges to the government and MPs.
- Could it be explained how the
business plan for Anglian Water had been set up without taking into
account the number of houses to be built within the local plan?
- The Pre-Development Planning Manager
commented that this will be included as part of their submission.
Where local plan figures had been used previously, these had been
rejected by the regulator who used Office for National Statistics
data.
- Would the money used for
infrastructure investment come from shareholders or borrowing?
- The Regional Engagement Manager
responded that it was a mixture of both, and the investment was
paid back to investors through billpayers over the life of those
assets.
- Was account taken of extra income
received from new properties?
- The Regional Engagement Manager
commented that Anglian Water were encouraging people to use less
water and use it more efficiently. The money from billpayers could
then be used to invest in future infrastructure assets.
- Queried the number of farms actually
on water meters.
- The Regional Engagement Manager
responded that Anglian Water had the highest density of water
meters in the UK, following a campaign to install as many of these
as possible.
- These were now starting to be
replaced with smart meters that had updated technology to help
customers better manage consumption and identify leaks.
- Were improvements made to storm
overflow systems paid for through billpayers?
- The Regional Engagement Manager
confirmed that the funding for these came from both shareholders
and ultimately billpayers.
- A list of improvements made within
the South Holland area would be provided.
- It seemed unfair on billpayers that
there had been a lack of investment by Anglian Water in the water
infrastructure within the district.
- The Regional Engagement Manager
responded that this was due to a mixture of the regulators capping
bills for a significant period of time and increased issues related
to climate change.
- It was noted that investment was
being caught up on in relation to WRC’s.
- Who was responsible for the collapse
of and unblocking of drains following a storm?
- The Regional Engagement Manager
confirmed that most road guilles/
drains were the responsibility of Highways, while foul sewers (and
some surface water drains) were Anglian Water’s
responsibility.
- It was noted that flooding
responsibility was a complex challenge across a lot of
organisations. Information would be shared with Members on who to
call if a flood occurred.
- Concern that shareholder dividends
had increased while bills had stayed the same.
- The Regional Engagement Manager
confirmed that shareholders took modest dividends of around 2.9%
return on average and they had recently committed to not taking a
dividend for the next four to five years.
- Had Anglian Water been in direct
contact with residents in hotspot areas for non-flushable items?
- The Regional Engagement Manager
confirmed that this was the case, with both door knocking and
posters being put up in streets.
- Individual properties could be
pinpointed, and Anglian Water did have powers of prosecution, but
the main focus was on education.
- Residents needed to be kept
accurately informed of how long works would be taking placed and
raised a particular issue in Spalding.
- The
Regional Engagement Manager agreed that this was fair feedback and
would remind repair teams to ensure a robust comms plan was in
place for future works.
- Would the new Lincolnshire Reservoir
be connected the SPA project, and if so, would the majority of the
water be going to Cambridgeshire?
- The Regional Engagement Manager
confirmed that they would be connected but the water would go into
the network to be used wherever needed.
- Having a reservoir would also become
a go-to destination with a visitor centre, walkways and leisure
facilities being considered.
- Asked about use of water butts to
water gardens.
- The Regional Engagement Manager
advised that Anglian Water had a partnership scheme to retrofit
water butts in some flooding hot-spot locations.
Following the presentation, Members wished for
the following comments to be passed to the Planning Department:
- There was a need to create more
awareness of the water infrastructure issue and the case law and
legislation to back up this decision.
- Ask officers to investigate the
validity of pre-commencement conditions suggested by Anglian
Water
- Explain what the effects of
restriction of connection at some water recycling centres would
have on future plans for delivery.
- What sort of consequences would the
authority expect from central government should the number of
required houses not be delivered.
A briefing note from the Assistant Director
– Planning and Strategic Infrastructure on this issue would
be provided to the next meeting of the Performance Monitoring
Panel.