|
Planning No. and
Applicant
|
Proposal
|
|
H05-0439-25 National Grid Electricity
Distribution
|
Full application for use of site to construct
new primary substation at Land West of Branches Lane, Holbeach,
Spalding.
|
Consideration was given to the report of the
Development Manager upon which the above application was to be
determined, including their recommendations, copies of which had
previously been circulated to all members.
Members debated the matter and fully explored
the details of the application in light of prevailing policies and
guidance, with the following comments being raised:
- The temporary car park had been
shown on the plan but not mentioned on the report. Would this be
conditioned to ensure it was restored to agricultural land?
- Officers responded that if planning
consent were granted, temporary access and car parking would
generally be covered by permitted development rights so would only
require separate consent if it were to become a permanent
feature.
- Requested that underground cabling
be made a condition to avoid pylons being put in place.
- Officers confirmed that electrical
infrastructure was covered by permitted development rights and
pylon construction could not be controlled through planning
conditions in this case.
- Disappointed that suggested hedging
on the north side was discounted.
- Questioned the need for a substation
in Fleet that would service Holbeach and why other sites had not
been looked into.
- Officers confirmed that the
applicant had provided a statement that explained the process of
choosing the site and how other sites were discounted.
- Queried why the application was
referred to Chairman’s Panel first rather than automatically
being presented to Planning Committee, given SHDC’s strong
support.
- Officers responded that SHDC was not
the applicant or the landowner and therefore constitutionally, the
application was correctly presented to Chairman’s Panel
first.
- It was also added that the SHDC had
been involved in assessing district-wide energy needs which had
shown that current network capacity would be exhausted by 2027 and
an upgrade was required in this area, not the choosing of a
particular site.
- The Council’s involvement in
this application was strategic, based on energy capacity planning
rather than operationally choosing a site. Without a new substation
the district would not be able to deliver housing and industry at
the levels set out in the Local Plan.
- Would the building itself ensure
that noise levels from operation were kept to a minimum?
- Officers responded that there was a
condition included for a construction management plan but in terms
of the operation of the substation, the Council’s
Environmental Protection team had not raised any concerns.
- The notion that this building was
visually similar to agricultural buildings across the district and
therefore didn’t need to be screened was incorrect as most
agricultural buildings were expected to have some sort of
screening.
- Were the conditions relating to any
screening and biodiversity actually enforceable?
- Officers confirmed that they were
enforceable, and the screening involved would be a landscaping
scheme to soften the visual impact rather than full screening.
- Could the landscaping condition go
further to insist that screening was put in place on all sides of
the building?
- Officers responded that there were
two separate conditions included for landscaping and boundary
treatments. Discussions had been undertaken with the applicant
around further planting but this was not possible within the
confines of the site.
- There was a danger that a more
stringent condition could lead to the substation not being
built.
- Welcomed the update to energy
infrastructure in South Holland.
- Lincolnshire Fire and Rescue had
objected with regard to fire hydrants, was a condition included to
overcome this?
- Officers confirmed that this would
be secured through the building regulations scheme rather than a
planning condition.
- The application stated that there
were no hazardous materials on site. Was this correct given that
the transformers would be filled with mineral oil?
- Officers confirmed that this part of
the application form related to existing site conditions.
- Suggested that the wording on
condition four be amended to read ‘prior to consent of
use’ rather than ‘occupied’.
- Officers confirmed that this could
be amended if the Committee agreed to this.
- Would access and highways
improvements be completed prior to the consent of use or done prior
to construction? The condition also stated that the signing off of
the completion of works would be done by the local planning
authority, should this not be the highways authority?
- Officers responded that final
highways and access improvements would usually be done prior to the
consent of use.
- The applicant would be required to
submit an application to the local planning authority to discharge
the condition. As part of this process the highways authority would
be consulted, and the local planning authority would then discharge
the condition.
- The wording of condition four could
be amended to ensure it was clear there was a requirement for the
applicant to submit an application to discharge the condition.
The full debate was not repeated here as a
livestream of this Planning Committee Meeting could be viewed on
South Holland District Council’s Facebook page for a limited
period of time, in line with the Democratic Services Privacy
Notice.
AGREED:
That permission be granted subject to the
conditions outlined at section 9.0 of the report, and the following
amendments to condition four:
·
Word ‘occupied’ to be replaced with ‘prior to
consent of use’
·
Addition of wording to make it clear the applicant was required to
submit an application to discharge the condition.
(Moved by Councillor Bingham, Seconded by
Councillor Beal)
Oral representations were received in respect
of the above application in line with the Council’s scheme of
public speaking at Planning Committee meetings:
Supporter: Paul Greco (NGED)
(Applicant)