Planning No. and
Applicant
|
Proposal
|
|
H09-0721-25 D Brown (Building Contractors)
|
Full application for development of 57
affordable dwellings with associated access, open space and
drainage at Land South of Wignals Gate, Holbeach, Spalding.
|
Consideration was given to the report of the
Development Manager upon which the above application was to be
determined, including their recommendations, copies of which had
previously been circulated to all members.
Members debated the matter fully, with the
following comments being raised:
- Concern was expressed that, whilst
the benefits of affordable housing were recognised, a 100%
affordable housing scheme conflicted with the principle of creating
mixed and balanced communities. Reference was made to previous
discussions on other schemes where concerns had been raised
regarding the concentration of affordable housing.
- Concern was raised about the design
and layout of the development, and that the scheme appeared to
facilitate future expansion through roads terminating at the site
boundaries without the support of a wider masterplan. It was also
considered that the development failed to provide a sympathetic
transition to the countryside, relying heavily on close-boarded
fencing rather than softer landscaping measures.
- Further concerns were raised
regarding the site entrance, which was viewed as lacking a clear
focal point and being dominated by an attenuation basin, whilst
drainage features were not considered to be fully integrated into
the overall design.
- Concern was also expressed regarding
the lack of a clear street hierarchy, the extensive use of hard
surfacing and the presence of large parking courts with limited
landscaping.
- It was raised that the proposal
would fail to respect the character of Wignals Gate, fail to
establish an appropriate rural edge and fail to deliver a
high-quality design solution.
- It was suggested that, should
planning permission be granted, additional conditions be imposed to
secure enhanced landscaping throughout the site, including native
hedgerows, additional tree planting, and landscaping within parking
courts. Further improvements were requested in relation to hard
surfacing proposals, the design and quality of open spaces,
adequate bin storage provision and the implementation of a
comprehensive lighting scheme to ensure both safety and visual
amenity.
- Concerns were raised regarding the
density of the development, estimated at approximately 13 dwellings
per acre, and whether this reflected the character of surrounding
development.
- Officers confirmed that the
development would have a gross density of approximately 34.5
dwellings per hectare.
- Concern was also expressed regarding
the absence of contributions sought by the NHS and Lincolnshire
County Council for education provision, with the view that any
resulting funding gap would ultimately need to be met through
public resources.
- Further concerns were raised that
the density and scale of development appeared out of keeping with
surrounding residential properties and that the proposal could
result in a large estate adjoining existing housing and open
countryside.
- Clarification was provided that the
application site formed part of a wider reserve allocation with an
indicative capacity of 70 dwellings. The allocation covered a
larger area of land than the application site and had originally
envisaged a mixed-tenure development.
- Concerns were raised regarding the
future management and maintenance of the development, including
open spaces, landscaping and communal areas. Questions were asked
regarding the ability of the housing association to maintain
standards over the long term.
- Officers advised that housing
associations had a vested interest in maintaining developments as
long-term assets and are subject to regulatory oversight. It was
also noted that wholly affordable housing schemes are relatively
uncommon and that many developments instead seek reductions in
affordable housing provision.
- Concerns were raised regarding the
effectiveness of management companies and housing associations in
maintaining landscaping and communal areas, together with requests
for additional litter bins and suitable bin storage arrangements.
- Officers assured the committee that
the proposed housing association was a regulated registered
provider with responsibilities for maintaining housing stock and
communal areas and that local lettings policies would assist in
achieving balanced communities.
- Concerns were also raised regarding
the absence of renewable energy measures, including solar panels
and air-source heat pumps, and the adequacy of parking
provision.
- It was acknowledged that affordable
housing need remained significant and that the success of such
developments often depended on effective management arrangements.
Support was expressed for stronger landscaping proposals, enhanced
boundary treatments and improved arrangements for litter bins and
waste storage.
- Officers advised that planning
conditions already required details of landscaping and hard and
soft surfacing, although these could be strengthened if considered
necessary. Additional requirements relating to bin storage could
also be secured by condition.
The initial vote to approve the
application was lost. Following further debate, a motion to defer
the application for further discussions between officers and the
developers on layout and design was tabled.
AGREED:
That the application be deferred for further
discussions to take place between officers and the developer
regarding the layout and design.
(Moved by Councillor Brewis, Seconded by
Councillor T Sneath)
Oral representations were received in respect
of the above application in line with the Council’s scheme of
public speaking at Planning Committee meetings:
Supporter: Chris Lindley (Agent)